The layers for the full installation are as follows:
- Bottom: 8-10" of compressed crushed rock aggregate (may already exist)
- 2" polystyrene insulation
- 2-3" layer of concrete
- Rebar and/or reinforcing mesh and attach the cable or mat
- Top: Pour a 2-3" layer of concrete as the final flooring surface
Call tech support at (800) 875-5285 to customize this to your unique application.