The layers for the full installation are as follows:

  • Bottom: 8-10" of compressed crushed rock aggregate (may already exist)
  • 2" polystyrene insulation
  • 2-3" layer of concrete
  • Rebar and/or reinforcing mesh and attach the cable or mat
  • Top: Pour a 2-3" layer of concrete as the final flooring surface

Call tech support at (800) 875-5285 to customize this to your unique application.